Occupied apartment blocks, offices, schools, healthcare settings, hotels, restaurants, theatres, warehouses and industrial units cannot all be programmed in the same way. Tell us about residents or tenants, security, inductions, permits, restricted hours, locked risers, ceiling access, working height, stored goods and live operations. These details affect how work is grouped and accessed, even when the penetration detail itself is similar.
Mechanical and electrical trades also need to be considered. Sealing too early can lead to completed fire stopping being disturbed by another cable or pipe; sealing too late can leave openings hidden above ceilings or hold up inspection. A useful sequence identifies completed routes, routes that may still change and the date each area becomes inaccessible.